Cant approve a new supplier after I have made changes to the SPQ

I updated the Supplier Profile Questionnaire, I added some new questions and update others, once I know these are working in the test site I will be require to make them in the live site.

I "ok" the changes and published the template.

Done nothing different to what I've done before.

I then created a test supplier via the test self-registration link to make sure the questions were pulling through for the supplier – these worked fine.

As the supplier I submitted the SPQ.

I then logged back on as me to approve this new supplier and I get the following message:

"You must complete all predecessor tasks before you can start the approval task for new supplier organisation"

Can you let me know what this means – as I can't approve this supplier.

I've done this 3 times now and I cant approve any of my test suppliers.

 

 

Does changing the template has anything to do with any further prerequisite?